Power and cooling density:
-
Power and cooling were
defined as w/ft2 or W/m2 or British thermal units (BTU)/hr or KW/hr, but the
true density should be determined by KW/rack.
-
High density is above
10KW/rack.
-
Medium density is from 4
KW/rack up to 10 KW/ rack.
-
Low density is up to 4
KW/rack
-
Previously the measurement
of cooling was by Tons
-
Tons are related to the
quantity of ice used to cool.
-
To change from Ton to Kwc.
KWc= Ton x 3.516
Levels of redundancy:
-
N – is need and meets base
requirements with no redundancy.
-
N+1 – is one additional
unit/path/Module more than the base requirement.
-
2N – is two complete
units/paths/modules of every one required for the system base.
-
2(N+1) – Two complete (N+1)
units/module/paths if there is any failure of one system still leaves and
entire stem still working.
Criticality Classification:
-
N = Single path “No
Redundancy”
-
N+1 = Single path with some
redundancy
-
2N = Concurrently
maintainable
-
2(N+1) = Concurrently
maintainable with full fault tolerant-
Availability rating:
99% annual
time unavailable = 88 hours
99.9% annual
time unavailable = 8.8 hours
99.99% annual
time unavailable = 53 Minutes
99.999% annual time unavailable = 5.3 minutes
99.9999% annual time unavailable = 32 seconds
Uptime Institute Tier IV is 99.995% or 26 minutes/year
Metrics.
The main
power efficiency metrics currently in use within the dc industry are based on
the “ratio of IT load to Facilities load”
-
This is referred to as the
facility efficiency.
-
Two commonly used metrics
are PUE & DCiE
Data center infrastructure efficiency
DCiE = (IT load) / (Total facility load) x 100%
Power Usage Effectiveness
PUE = (Total facility load) / (IT load)
What is the IT load?
This relate
to the power consumption of all of the IT equipment within the data center.
What is the facility load?
This
related to the mechanical and electrical systems that support the IT electrical
and such as cooling systems (Chiller plant, fans, pumps) air conditioning units,
UPS, PDUs etc.
PUE Version 2 has 4 Categories:
PUE0 =This
is still power (KW), but uses case measurements (highest peak measured)
PUE1 =This
is annualized energy measured at the output of the UPS (Lowest accuracy).
PUE2 =This
is annualized energy at the output of the PDU (better accuracy)
PUE3 =This
is annualized energy at the rack/input of IT equipment (best accuracy)
Future metrics
CUE : Carbon usage effectiveness
(Green Grid)
WUE : Water usage effectiveness
(Green Grid)
CADE : Carbon average data center
efficiency (Uptime inst.)
DPpE : Data Center performance per
energy (Green IT promotion Council)
No comments:
Post a Comment